UPDATE MAY 1, 2017

Things are progessing nicely and the new restrooms are open!  We are planning a ribbon cutting ceremony on June 21, 2017 so mark your calendars!

UPDATE MARCH 20, 2017

RAIN RAIN GO AWAY! If you have been by the spray park lately, not too much has changed. The contractor is on hold waiting for the next weather window where temperatures are above 50 degrees, for 24 hours and there is NO rain so that the stain and the sealer can go down on the pad.

It’s been frustrating, but we are hopeful that the weather will change and we can wrap up the construction on the project.

YES, we are still opening the park and restroom by late spring.

Our fundraising goal  of$180,000 has almost been met, we have raised $174,335. To make a donation you can contact nicolej@cityofanacortes.org or go online http://anacortesparksfoundation.org/donate/

 Hang in there…

 This new addition to our community will be worth the wait!

 Questions, feel free to contact Project Manager Nicole Johnston at nicolej@cityofanacortes.org or 360-299-1967.

-------------------------------------------------------------------------------------------

Bid Opening to Hire a Contractor for the project is set for Tuesday, August 30th. Once the contractor is hired we will move on this project as fast as we can, with the install of the restroom happening first.

Spray Pad is still set to be ready for the Spring of 2017.

We currently have fundraised $104,000.00 reaching closer to our goal of $180,000.00 

Questions?  Please contact Project Manager, Nicole Johnston at nicolej@cityofanacortes.org or call 360-299-1967. 

To make a donation you can visit the Anacortes Parks Foundation http://anacortesparksfoundation.org/