Thompson Trail Retrofit Project
Wilder Construction of Everett will begin the final portion of the Thompson Trail project. Beginning at 12th and Q with the Q Avenue Reconstruction, the trail continued through the industrial zone and extended to the shoreline. The Trestle Retrofit will complete the link to March’s Point Road allowing pedestrians and cyclists a safer commute on North Fidalgo Island. Work will include:
- remove damaged railroad ties
- install deck support structure as needed
- construct 12 ft. wide composite deck and observation areas
- install pedestrian and bicyclist safety guardrail
Key Dates
Contract Bid Opening May 18, 2005
Contract Award May 23, 2005
Notice To Proceed June 16, 2005
Construction Start June 20, 2005
Construction Complete October 17, 2005
Project Contacts
City Project Manager
Kim McKinnon, 360.293.1920
City Project Inspector
Jim Baldwin, 360.299.1972
Funding
This portion of the project will be funded by City transportation funds and the Washington State Interagency Committee (IAC) for outdoor recreation. The estimated construction cost is $564,395.
|